GEOGRID INSTALLATION For taller or
more critical walls that require use of geogrid,
continue the installation process with step 5. If
geogrid is not required, skip to step 6.
Step 5A. Excavate Reinforced Soil
Area Remove existing soils in the
reinforced soil area to the maximum embedment
length of the geogrid design. Provide a generally
level soil condition behind the wall units for the
placement of each geogrid layer.
Step 5B. Cut Geogrid. Cut sections
from geogrid roll to the specified length
(embedment depth). Geogrid roll direction is from
the wall toward the embankment. Check
manufacturer's criteria for biaxial or uniaxial
geogrids. In most cases correct orientation is to
roll the geogrid perpendicular to the wall
face.
Step 5C. Install Geogrid. Hook
geogrid over the Keystone fiberglass pins to
ensure a positive mechanical connection between
the unit and geogrid.
Step 5D. Secure Geogrid. Pulled the
pinned geogrid taut to eliminate loose folds.
Stake or secure back edge of geogrid before and
during backfill and compaction. Remove stakes, if
desired, once backfill is placed. Place additional
sections of geogrid, abutting each other, for
continuous coverage at each layer.
Step 5E. Install Next Course of Keystone
Units.
Step 5F. Place Compacted Backfill Over
Geogrid In 8" Lifts. Provide a mimimum of
6" (150mm) reinforced fill coverage prior to
driving equipment over the geogrid with tired
equipment. Avoid driving or turning vehicles
directly on geogrid to avoid excessive
damage. |